Triangular Distribution and Beta Distribution in Three-Point Estimation (PERT)

Triangular Distribution and Beta Distribution in Three-Point Estimation (PERT)

Description
Three-point estimation is a common technique in project management used to estimate activity durations by considering three scenarios—most optimistic, most likely, and most pessimistic—to improve estimation accuracy. This method primarily addresses task uncertainty. Within three-point estimation, two main probability distribution models are widely used: the triangular distribution and the beta distribution (also known as the PERT distribution). Understanding the differences, calculation methods, and applicable scenarios of both is crucial for developing realistic and feasible project plans.

Problem-Solving Process

  1. Understanding the Three Basic Estimates
    First, we need to define three time estimates for each activity:

    • Optimistic Time (O): The shortest possible time required to complete the activity under ideal conditions with no problems encountered.
    • Most Likely Time (M): The most frequently occurring time under normal circumstances. It has the highest probability of occurrence.
    • Pessimistic Time (P): The longest possible time required to complete the activity under nearly all unfavorable conditions.

    Example: Suppose we are estimating the time for "Developing the Login Feature."

    • O (Optimistic Time) = 5 days
    • M (Most Likely Time) = 8 days
    • P (Pessimistic Time) = 14 days
  2. Mastering the Calculation and Application of Triangular Distribution

    • Core Concept: The triangular distribution is a simple model that assumes the expected activity duration (mean) is the arithmetic average of the three estimates. It does not assign special weight to the "Most Likely Time."
    • Calculation Formula:
      Expected Duration (Te) = (O + M + P) / 3
    • Calculation Example:
      Using the data above: Te_triangle = (5 + 8 + 14) / 3 = 27 / 3 = 9 days
    • Characteristics and Applicable Scenarios:
      • Advantages: Very simple and intuitive to calculate.
      • Disadvantages: Assumes all three points (O, M, P) are equally likely, which may not be accurate in real projects as it ignores the special status of the "Most Likely Time" M.
      • Applicability: Often used for quick estimations when historical data is insufficient or when activity uncertainty is relatively low.
  3. Mastering the Calculation and Application of Beta Distribution (PERT Distribution)

    • Core Concept: The beta distribution is a more complex and commonly used model, originating from the Program Evaluation and Review Technique (PERT). The core of this model is that it gives greater weight to the "Most Likely Time" M, considering its influence on the final outcome to be greater than that of O and P. It also adjusts for pessimistic and optimistic times to better reflect real-world probability distributions (which are often not symmetric).
    • Calculation Formula:
      Expected Duration (Te) = (O + 4M + P) / 6
      This formula can be interpreted as assuming the Most Likely Time (M) occurs four times, while the Optimistic and Pessimistic times each occur once when calculating the average.
    • Calculation Example:
      Using the same data: Te_beta = (5 + 4*8 + 14) / 6 = (5 + 32 + 14) / 6 = 51 / 6 = 8.5 days
    • Characteristics and Applicable Scenarios:
      • Advantages: More aligned with the statistical patterns of actual projects, providing generally more accurate estimates than the triangular distribution, especially for high-uncertainty activities.
      • Disadvantages: Slightly more complex calculation.
      • Applicability: This is the standard method in three-point estimation, widely used in various projects, particularly when activity duration uncertainty is high.
  4. Comparative Analysis and Selection

    • Result Comparison: In our example, the triangular distribution yields 9 days, while the beta distribution yields 8.5 days. This difference illustrates the varying emphasis the two models place on the "Most Likely Time."
    • How to Choose:
      • Use the triangular distribution for quick estimates when historical data is lacking or when the activity duration distribution is believed to be symmetric (i.e., O and P deviate from M to roughly the same degree).
      • In most cases, especially when activities have significant uncertainty and their duration distribution is likely asymmetric, the beta distribution (PERT) is recommended as it provides more reliable and realistic estimates.
    • Supplement: Standard Deviation Calculation
      In addition to calculating the expected time, the beta distribution conveniently allows for calculating the activity's standard deviation (σ), which measures its uncertainty or risk.
      Standard Deviation (σ) = (P - O) / 6
      In our example: σ = (14 - 5) / 6 = 9 / 6 = 1.5 days
      A larger standard deviation indicates higher risk and uncertainty for the activity.

Summary
Three-point estimation effectively handles uncertainty in project estimation by considering the best, most likely, and worst-case scenarios. Among them, the triangular distribution calculates via a simple average and is suitable for quick or low-uncertainty estimations; whereas the beta distribution (PERT) provides a more precise and commonly used estimation method through weighted averaging (giving more weight to the most likely time). In practical projects, project managers should select the appropriate model based on the characteristics of the activities and the availability of data.